COST CONTROL OF PROJECTS
Cost
control aims at ensuring that resources are used to best advantage.
A
client may define cost control as keeping the costs of a project within budget.
Rising
prices, high interest rates and restrictions on use of capital have caused
employers to demand that professional advisers should accept cost as an element
in design as well as accurately forecast overall costs.

This
involves close collaboration between the architect and quantity surveyor and
other professionals.
COSTS TO BE CONTROLLED
The following is a list of
costs to be controlled:
1.
Materials
2.
Labour
3.
Overheads
The
labour and materials associated with a project can be controlled in several
ways.
Careful
planning and programming of the project will help to control these elements.
One
method that can be employed is ‘just in time
management’
This
ensures that both labour and materials are available just at the right time.
For
this to happen an accurate programme should be used to calculate the labour
requirement at all times throughout a project.
The
materials required at any time during a project can be ascertained from drawings, specifications
and B of Q’s and purchased or pre-ordered in
time for installation.
The
draw back of this method is that there is little room for error and if it is
misjudged then tradesmen could be sitting around with no materials to install.
One
of the advantages of ‘just
in time management’ is that materials do not have to be stored for long
periods, if at all, therefore reducing risk of loss and theft.
PROFIT
The profit for a particular
contract may be calculated as the total sum of money remaining from income
after paying for the cost of the work done including general overheads.
Profit
= Income - Project
Cost - Overheads
PROFIT MARGIN
This can be expressed as a
percentage of the cost of the work done.
Profit Margin =
Profit / Project Cost x
100%
The Project Cost or the cost
of the work done may or may not include overheads –
this should be made clear
when giving a figure for profit margin.
In practice the profit margin
may be from 2% to 5% for many projects.
Example 1
Calculate
the profit and profit margin for a project given the following information.
DATA:
Monthly Incomes totalled = £155,000
Total Materials cost = £48,500
Total Labour cost = £74,200
Total Company overheads = £7,800
Total Site overheads = £16,250
ANSWER
Total
overheads = £7,800 + £16,250
= £24,050
Project
Cost = £48,500 + £74,200 = £122,700
Profit
= Income - Project Cost
- Overheads
Profit = £155,000 -
£122,700 - £24,050
Profit =
£8,250
Profit Margin = Profit /
Project Cost x 100%
Profit
Margin = £8,250 / £122,700
x 100%
= 6.72 %
say 6.7 %
Example 2
Calculate
the profit and profit margin for a project given the following information.
DATA:
Project duration = 12 months
Total Materials cost = £134,800
Total Labour cost = £275,200
Total Company overheads = £44,900
Total Site overheads = £87,250
Monthly Incomes:
|
|
|
Month Mar Apr May Jun Jul Aug |
|
Income £12,400 £34,000 £45,000 £47,700 £75,400 £56,200 |
|
Month Sept Oct Nov Dec Jan Feb |
|
Income £37,800 £67,500 £62,800 £89,700 £27,500 £23,200 |
TOTAL
INCOME =
£579,200
Total
overheads = £44,900
+ £87,250 =
£132,150
Profit
= Income - Project Cost
- Overheads
= £579,200 - £410,000 - £132,150
= £37,050
Profit Margin =
Profit / Project Cost x
100%
Profit
Margin = £37,050 / £410,000 x
100%
= 9.04 % say 9 %
PROJECT OVERHEADS
This is the cost of administering a project and
providing general plant, site staff, facilities and site based services.
Overheads include:
1. Staff - most
costly item of overheads.
2. Transport - ferry
men to site.
3. Overtime - abnormal
overtime.
4. Training - Health
and safety, first aid, COSH, specialist systems.
5. Welfare - protective
clothing.
6. Accommodation - A sub-contractor may be charged by the
main contractor for site offices, toilets, canteen and stores.
7. Site
transport - plant to and from site, trucks, dumpers, etc.
8. Large
plant - buying,
hiring, fuel.
9. Small
plant - tools,
drills, compressor.
10. Scaffolding - buy
or hire.
11. Temporary
services - all incoming services.
12. Services
charges - electricity, telephone, water, gas.
13. Defects liability cost - probable
cost is related to labour and materials value.
14. Hand
over and cleaning - quotation from cleaning company may be
possible.
15. Security - lock-ups,
store, security company.
16. Signage - sign
boards, notices, and advertising.
17. Cleaning
site - periodic
removal of rubbish.
18. Entertainment - promotions,
parties.
19. Sundry
items - testing apparatus and materials.
On a large construction project a distinction is
usually made between site overheads and company overheads.
The contractor may be reimbursed for his site overheads
by means of the contract preliminaries or sometimes by sums added to the rates
in a Bill of Quantities.
Company overheads can be calculated separately, and are a budgeted
amount calculated on the anticipated year’s expenditure on staff, offices,
equipment, stationary and the like.
Typical
overheads are 5% to 7.5% of project cost.
Typical
site overheads are 10% to 20% of project cost.
Sometimes
company overheads are calculated as a percentage of annual
turnover for accounting procedures.
PLANT
Estimating for the plant
element depends on whether the contractor owns or has to hire the required
machinery.

OWNED PLANT
An hourly rate for the machinery should be calculated
based on the following:
1.
Depreciation
2.
Lost
interest on the initial cost or interest charges to borrow capital.
3.
Cost
of repairs & maintenance.
This will give a total annual cost for owning the
machine.
An hourly rate can be
arrived at by dividing this annual cost by the number of hours the machine is
operating. This can be obtained from the plant records.
HIRED PLANT
A true hire charge should be worked out based on the
total time that the plant is hired against the time it is actually employed on
productive work.
Example 3
1.(a) Calculate whether it is cheaper to hire or buy a pipe threading
machine for steel pipes.
1.(b) Calculate the hourly rate for buying and hiring the machine.
DATA:
Length of contract = 18
months or 72 working weeks
Cost of machine
new = £6500.00
Depreciation = 50% per annum.
Repairs /
maintenance = £480.00 per annum.
Hire charge per
week = £85.00
Interest rate = 5%
Plant records show productive machine usage to be 10 hours per
40 hour working
week on average.
ANSWER 1.(a)
Buying
Capital Expenditure = £6500.00
Depreciation = £4875.00 ( 50% + 25%
= 75% x £6500 )
Residual value = £1625.00
Repairs = £ 720.00 ( £480
x 1.5 years )
Lost interest on capital
outlay = £ 325.00 ( 5% x £6500
= £325 )
Final cost = Depreciation +
Repairs + Interest
Final cost = £
4875.00 + £720.00
+ £325.00
Final cost = £ 5920.00
Hiring
£85 per week x 72 weeks = £6120.00
Therefore it is cheaper to
purchase the machine @ £6500.00 since it will have a residual value at the end
of the project.
ANSWER 1.(b)
The annual hours of machine
usage are: (10/40) x
(72/1.5) = 480 hours per annum.
Buying
the machine costs: £5920 / 480 =
£12.33
per hour (actual hours worked)
Hiring the machine costs: £6120
/ 480 = £12.75 per hour
(actual hours worked).
Example 4
Calculate whether it is
cheaper to hire or buy a mini excavator given the following information.
DATA:
Length of contract = 25
weeks
Cost of machine
new = £18,000.00
Depreciation = 20% in the first 10 weeks then 0.5% per week.
Repairs /
maintenance = £400.00 per service, 1 service required.
Hire charge per
week = £200.00
Interest rate = 5% per annum

ANSWER
Buying
Capital Expenditure = £18,000.00
Depreciation = £ 4950.00 ( 20%
+ (15 x 0.5%) = 27.5%
x £18,000 )
Residual value = £13,050.00
Repairs = £ 400.00
Lost interest on capital
outlay = £ 433.00 (
(25/52) x 5% x
£18,000 = £433 )
Final cost = Depreciation +
Repairs + Interest
Final cost = £
4950.00 + £400.00
+ £433.00
Final cost = £ 5783.00
Hiring
£200 per week x 25 weeks = £5000.00
Therefore it is cheaper to
hire the machine.